Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1,000, is
Fantastic news! We've Found the answer you've been seeking!
Question:
- Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1,000, is 50% complete, and has actually cost $700 so far. Activity C is worth $100, is 75% complete, and has actually cost $90 so far. What is the total earned value for the project?
Using the information above, calculate the Cost Performance Index (CPI) for the project.
- Your project is scheduled to last 3 months and cost $100,000. At the end of the first month, the project is 25% complete. What is the Earned Value?
- CPI greater than one implies that.....
- How much we will be over or under budget at the end of the project; is expressed by?
Related Book For
Income Tax Fundamentals 2013
ISBN: 9781285586618
31st Edition
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill
Posted Date: