Question: Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1,000, is 50% complete, and has actually cost $700 so
- Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1,000, is 50% complete, and has actually cost $700 so far. Activity C is worth $100, is 75% complete, and has actually cost $90 so far. What is the total earned value for the project?
Using the information above, calculate the Cost Performance Index (CPI) for the project.
- Your project is scheduled to last 3 months and cost $100,000. At the end of the first month, the project is 25% complete. What is the Earned Value?
- CPI greater than one implies that.....
- How much we will be over or under budget at the end of the project; is expressed by?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
