Question: Activity a m b (1-2) 2 2 8 (2-3) 1 1.5 11 (2-4) 0.5 1 7.5 (3-5) 1 2.5 7 (3-6) 1 2 3 (4-5)
| Activity | a | m | b |
| (1-2) | 2 | 2 | 8 |
| (2-3) | 1 | 1.5 | 11 |
| (2-4) | 0.5 | 1 | 7.5 |
| (3-5) | 1 | 2.5 | 7 |
| (3-6) | 1 | 2 | 3 |
| (4-5) | 6 | 7 | 8 |
| (4-6) | 3 | 4 | 11 |
| (5-6) | 4 | 6 | 8 |
A. Draw the network diagram.
B: Find the average expected time and variance of each activity.
C. Determine the critical path.
D. Formulate the project as a linear programming problem.
E. What is the probability that activity (1-2) will be completed in at most 2 days?
F. What is the probability that the entire project will be completed in 25 days or less?
G. When will the project be completed , if we are %95 sure it will be completed in the given specified time.