Question: Activity Activity ID Predecessor Duration (weeks) Order review None 3 B Order standard parts A 15 Produce standard parts A 10 D Design custom parts


Activity Activity ID Predecessor Duration (weeks) Order review None 3 B Order standard parts A 15 Produce standard parts A 10 D Design custom parts A 18 E Software development A 13 F custom C, E 15 Manufacture hardware G Assemble B, F 10 H Test E, G 6 a. Draw a neat project network, b. Present in a table or on the network diagram- Early Start, Early Finish, Late Start, Late Finish dates, Slack, and Critical and non- critical activities c. What is the critical path, and what is the minimum duration to complete the project