Question: Activity Activity Legend Activity Predecessor Activity Duration Design house and obtain financing 1 - 3 Lay foundation 2 1 2 Order and receive material 3

Activity

Activity Legend

Activity Predecessor

Activity Duration

Design house and obtain financing

1

-

3

Lay foundation

2

1

2

Order and receive material

3

1

1

Build house

4

2,3

3

Select Paint

5

2,3

1

Select Carpet

6

5

1

Finish work

7

4,6

1

  1. Draw an AON Diagram.
  2. Find out the critical path.