Question: Activity Activity Legend Activity Predecessor Activity Duration Design house and obtain financing 1 - 3 Lay foundation 2 1 2 Order and receive material 3
| Activity | Activity Legend | Activity Predecessor | Activity Duration |
|
| Design house and obtain financing | 1 | - | 3 | |
| Lay foundation | 2 | 1 | 2 | |
| Order and receive material | 3 | 1 | 1 | |
| Build house | 4 | 2,3 | 3 | |
| Select Paint | 5 | 2,3 | 1 | |
| Select Carpet | 6 | 5 | 1 | |
| Finish work | 7 | 4,6 | 1 |
- Draw an AON Diagram.
- Find out the critical path.