Question: Activity # Activity Name Predecessor Duration [Days] 1 A - 5 2 B - 6 3 C A 4 4 D A, B 5 5
Activity # Activity Name Predecessor Duration [Days] 1 A - 5 2 B - 6 3 C A 4 4 D A, B 5 5 E C 6 6 F C, D 10 7 G E 4 8 H F, G 3 Based on the table above, draw the network diagram for this project. Include the activity number, name and duration. You can do it on paper or in Excel. Once done, save the file or make a screenshot and attach the file below.