Question: Activity Activity Time ( days ) Immediate Predecessor ( s ) A 2 - B 4 - C 4 - D 3 - E 7

Activity Activity Time (days) Immediate Predecessor(s)
A 2-
B 4-
C 4-
D 3-
E 7 A
F 4 B, C, D
G 4 E, F
H 5 F
I 5 G
J 3 G
K 2 H