Question: Activity Activity Time (days) Immediate Predecessor(s) A 3 - B 3 A C 5 A D 4 B E 1 B F 5 B, C
Activity Activity Time (days) Immediate Predecessor(s) A 3 - B 3 A C 5 A D 4 B E 1 B F 5 B, C G 2 D, E H 3 F I 5 F J 6 G, H, I

The critical path is _____ and the project duration is _______ days. (Enter your response as a whole number.)