Question: Activity Days Required Predecessor Activities A 3 - B 2 A C 5 A D 8 B , C E 4 B , C F
Activity Days Required
Predecessor Activities
A B A C A D B C E B C F D E
PLEASE SOLVE IN EXCEL SHEET
Consider the following set of activities:
A Draw the CPM network for this problem.
B Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity.
B What is the critical path?
D How long should it take to complete the project?