Question: Activity Days Required Predecessor Activities A 3 - B 2 A C 5 A D 8 B , C E 4 B , C F

Activity Days Required
Predecessor Activities
A 3- B 2 A C 5 A D 8 B, C E 4 B, C F 2 D, E
(PLEASE SOLVE IN EXCEL SHEET)
Consider the following set of activities:
A. Draw the CPM network for this problem.
B. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity.
B. What is the critical path?
D. How long should it take to complete the project?
Activity Days Required Predecessor Activities A 3