Question: Project Scheduling with Certain Time: Activity Immediate Time (weeks) predecessor A - 3 B A 5 C - 4 D C 6 E B, D
Project Scheduling with Certain Time:
| Activity | Immediate | Time (weeks) | |
| predecessor | |||
| A | - | 3 | |
| B | A | 5 | |
| C | - | 4 | |
| D | C | 6 | |
| E | B, D | 4 | |
| F | E | 3 | |
| G | B, D | 5 | |
| H | G | 6 | |
| I | H, F | 2 |
Solve the problem and enter your answers to the questions:
1. What are the activities of the critical path?
2. What is the expected completion time for the project (#of weeks)?
3. What is the slack of activity F?
4. What is the latest start time of activity A?
Be sure to enter your answers as follow:
For (1) show the activity letters of the critical path.
For (2): show the answer is # of weeks.