Question: Construct a network diagram for the project below, determine the float/slack for each activity, and then identify the critical path. How many days are needed
- Construct a network diagram for the project below, determine the float/slack for each activity, and then identify the critical path. How many days are needed to complete the project?
| Activity | Task time (in days) | Preceding activities |
| A | 2 | None |
| B | 4 | A |
| C | 5 | None |
| D | 4 | A |
| E | 5 | A |
| F | 6 | C |
| G | 4 | C |
| H | 7 | D |
| I | 2 | D |
| J | 5 | B,E,F,I |
| K | 4 | E,F,G,I |