Question: Construct a network diagram for the project below, determine the float/slack for each activity, and then identify the critical path. How many days are needed

  1. Construct a network diagram for the project below, determine the float/slack for each activity, and then identify the critical path. How many days are needed to complete the project?

Activity Task time (in days) Preceding activities
A 2 None
B 4 A
C 5 None
D 4 A
E 5 A
F 6 C
G 4 C
H 7 D
I 2 D
J 5 B,E,F,I
K 4 E,F,G,I