Question: Activity B D E F Immediate Predecessor None None A E A,B C,D Normal Time Cost/day (days) 3 450 300 200 100 500 600 ANNWA

Activity B D E F Immediate Predecessor None None
Activity B D E F Immediate Predecessor None None A E A,B C,D Normal Time Cost/day (days) 3 450 300 200 100 500 600 ANNWA Lower Time Limit 1 2 1 1 1 3 a) Draw a network diagram for this project. What is the critical path? How long will the project take, if no crashing takes place