Question: Activity A B D E F Immediate Predecessor None None A E A,B C,D Normal Time Cost/day (days) 3 450 4 300 3 200 2

Activity A B D E F Immediate Predecessor None
Activity A B D E F Immediate Predecessor None
Activity A B D E F Immediate Predecessor None None A E A,B C,D Normal Time Cost/day (days) 3 450 4 300 3 200 2 100 2 500 4 600 Lower Time Limit 1 2 1 1 1 3 b) Determine the least cost way to crash activities in order to complete the project in 11 days; in 10 days; in 9 days; in 8 days