Question: Activity B D E F Immediate Predecessor None None E A,B C,D Normal Time Cost/day (days) 3 450 4 300 3 200 2 100 2

Activity B D E F Immediate Predecessor None None
Activity B D E F Immediate Predecessor None None
Activity B D E F Immediate Predecessor None None E A,B C,D Normal Time Cost/day (days) 3 450 4 300 3 200 2 100 2 500 4 600 Lower Time Limit 1 2 1 1 1 3 c) Suppose the due date for the project is 5 days and a penalty of $500 a day is assessed for each day late. What is the optimal number of days to crash the project? Why