Question: activity b total slack time is 5 days if b delay 10 days how many day project completion time is delayed? a. 10 B. 0

activity b total slack time is 5 days if b delay 10 days how many day project completion time is delayed? a. 10

B. 0

C. 5

D. 15

E. 50

SHOW WORK PLEASE!