Question: activity b total slack time is 5 days if b delay 10 days how many day project completion time is delayed? a. 10 B. 0
activity b total slack time is 5 days if b delay 10 days how many day project completion time is delayed? a. 10
B. 0
C. 5
D. 15
E. 50
SHOW WORK PLEASE!