Question: 1. Activity B Total slack time is 5 days. If activity B delay 10 days how many days project completion time is delayed? A. 0

1. Activity B Total slack time is 5 days. If activity B delay 10 days how many days project completion time is delayed?
A. 0
B. 5
C. 10
D. 50
E. 15
2. which one is FALSE about quality?
A. improved quality improve response
B. improved quality increase scrap costs
C. improved quality improve price
D. improve quality improve productivity
E. improve quality improve reputation
please choose the correct answer and show explanation!