Question: activity A total slack time is 5 days. if activity A delay 10 days. how many days project completion time is delayed? please SHOW ALL
activity A total slack time is 5 days. if activity A delay 10 days. how many days project completion time is delayed?
please SHOW ALL WORK THANKS ALOT!