Question: Activity BCC 50 = a b f Predecessors a d C. C f, g Duration (days) 3 4 5 4 29 6 2 k If

If activity F was completed in 10 days instead of the estimated 9 days, how does this affect the completion of the project? a. Critical path and the total duration to complete the project remains the same. b. Critical path remains same and the total duration to complete the project changes to 19 days. c. Critical path changes but the duration to complete the project remains the same. d. Critical path changes and the total duration to complete the project changes to 17 days. Activity a b c d e f g h Predecessors Duration (days) Duration (days) 3 4 5 4 2 9 6 2 If activity F was completed in 10 days instead of the estimated 9 days, how does this affect the completion of the project? a. Critical path and the total duration to complete the project remains the same. b. Critical path remains same and the total duration to complete the project changes to 19 days. Critical path changes but the duration to complete the project remains the same. d. Critical path changes and the total duration to complete the project changes to 17 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts