Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration 5 . B ' s

Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 5. B's earliest finish is 18, while C's is 15. F's late start is 23. Which of the following is definitely TRUE?
C has no slack, and is critical.
C must be started after B is finished.
F is not critical, and has slack.
B has no slack, and is critical.
D is critical, and has a slack of five days.