Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration 5 . B ' s
Activity D on a CPM network has predecessors B and C and has successor F D has duration Bs earliest finish is while Cs is Fs late start is Which of the following is definitely TRUE?
Group of answer choices:
B has no slack, and is critical.
F is not critical, and has slack.
C must be started after B is finished.
D is critical, and has a slack of five days.
C has no slack, and is critical.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
