Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration B ' s earliest finish
Activity D on a CPM network has predecessors B and C and has successor D has duration
Bs earliest finish is while Cs is Fs late start is Which of the following is
definitely TRUE?
has no slack, and is critical.
F is not critical, and has slack.
must be started after is finished.
D is critical, and has a slack of five days.
C has no slack, and is critical.