Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration 5 . B ' s

Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 5. B's earliest finish is 18, while C's is 15. F's late start is 23. Which of the following is definitely TRUE?\