Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration 6 . B ' s
Activity D on a CPM network has predecessors B and C and has successor F D has duration Bs earliest finish is while s is Fs late start is Which of the following is definitely true?
Select one:
a Dis critical, and has zero slack.
b is completed before
C D has no slack but is not critical.
d is critical and has zero slack.
e is a critical activity.