Question: Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while

Activity D on a CPM network has predecessors B
Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is definitely true? O A. Fhas no slack but is not critical. OB. C is completed before B. O C. B is a critical activity OD. D has no slack but is not critical O E. D is critical, and has zero slack. Click to select your