Question: Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 4 days. B's earliest finish is 20,

Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 4 days. B's earliest finish is 20, while C's is 15. F's late start is 24. Which of the following is definitely TRUE?

C is completed before B.

F is not critical, and has slack of 24 days.

B has no slack and is critical.

D has slack and is critical..

C has no slack and is critical.