Question: Activity Description Immediate Predecessor(s) Optimistic (Weeks) Most Likely (Weeks) Pessimistic (Weeks) A --- 4 7 10 B A 2 8 20 C A 8 12
| Activity Description | Immediate Predecessor(s) | Optimistic (Weeks) | Most Likely (Weeks) | Pessimistic (Weeks) |
| A | --- | 4 | 7 | 10 |
| B | A | 2 | 8 | 20 |
| C | A | 8 | 12 | 16 |
| D | B | 1 | 2 | 3 |
| E | D, C | 6 | 8 | 22 |
| F | C | 2 | 3 | 4 |
| G | F | 2 | 2 | 2 |
| H | F | 6 | 8 | 10 |
| I | E, G, H | 4 | 8 | 12 |
| J | I | 1 | 2 | 3 |
- What is the activity variance along the critical path?
- What is the probability of completion of the project before week 42?