Question: Activity Duration A Hire workers 25 B Install equipment 12 C Order materials 32 D Test equipment 11 E Train workers 16 F Run pilot
| Activity | Duration |
| A Hire workers | 25 |
| B Install equipment | 12 |
| C Order materials | 32 |
| D Test equipment | 11 |
| E Train workers | 16 |
| F Run pilot tests | 14 |

Part A) What are the critical activities? how many weeks will it take to complete the project?
Part B) ow many weeks will it take to complete the project?
Length (weeks) Path A-E - B-D-F C-F