Question: Activity Duration (days) Predecessor Start 0 A 8 Start B 10 Start C 3 A D 6 A E 4 B,C F 7 B,C G

Activity

Duration (days)

Predecessor

Start

0

A

8

Start

B

10

Start

C

3

A

D

6

A

E

4

B,C

F

7

B,C

G

4

D,E

H

5

F

End

0

G,H

  1. Draw the AON network.
  2. What is the critical path?
  3. How long will it take to complete the project?
  4. Can Activity B be delayed without delaying the completion of the project? If so, how many days?

Given the table above and estimated activity times below

Activity

Optimistic

Most Likely

Pessimistic

A

6.5

7.5

14.5

B

8.5

10.5

12.5

C

2.5

3.5

4.5

D

5.5

6.5

8.5

E

3.5

6.5

9.5

F

5.5

7.5

9.5

G

3.5

4.5

6.5

H

4.5

5.5

7.5

  1. What is the probability that the project will be completed within (based on the path with the longest expected time)?
    1. 22 days?
    2. 23 days?
    3. 26 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!