Question: Activity Duration (days) Predecessor Start 0 A 8 Start B 10 Start C 3 A D 6 A E 4 B,C F 7 B,C G
| Activity | Duration (days) | Predecessor |
| Start | 0 | |
| A | 8 | Start |
| B | 10 | Start |
| C | 3 | A |
| D | 6 | A |
| E | 4 | B,C |
| F | 7 | B,C |
| G | 4 | D,E |
| H | 5 | F |
| End | 0 | G,H |
- Draw the AON network.
- What is the critical path?
- How long will it take to complete the project?
- Can Activity B be delayed without delaying the completion of the project? If so, how many days?
Given the table above and estimated activity times below
| Activity | Optimistic | Most Likely | Pessimistic |
| A | 6.5 | 7.5 | 14.5 |
| B | 8.5 | 10.5 | 12.5 |
| C | 2.5 | 3.5 | 4.5 |
| D | 5.5 | 6.5 | 8.5 |
| E | 3.5 | 6.5 | 9.5 |
| F | 5.5 | 7.5 | 9.5 |
| G | 3.5 | 4.5 | 6.5 |
| H | 4.5 | 5.5 | 7.5 |
- What is the probability that the project will be completed within (based on the path with the longest expected time)?
- 22 days?
- 23 days?
- 26 days?