Question: ACTIVITY DURATION ( DAYS ) DEPENDENCY START 0 - A 8 START B 5 A C 6 B , H D 8 C E 9

ACTIVITY
DURATION (DAYS)
DEPENDENCY
START
0
-
A
8
START
B
5
A
C
6
B,H
D
8
C
E
9
D,F
F
3
C,I
G
7
START
H
8
G
I
9
H
J
5
I
K
2
J
L
3
J
END
0
Determine the slack for activity J (in days).
3
2
0
6