Question: ACTIVITY DURATION ( DAYS ) DEPENDENCY START 0 - A 8 START B 5 A C 6 B , H D 8 C E 9
ACTIVITY
DURATION DAYS
DEPENDENCY
START
A
START
B
A
C
BH
D
C
E
DF
F
CI
G
START
H
G
I
H
J
I
K
J
L
J
END
Determine the slack for activity J in days