Question: Activity Duration Dependency activity duration dependency A 5 B 6 A C 4 A D 2 A E 5 B F 3 B G
"
Activity Duration Dependency
| activity | duration | dependency |
| A | 5 | |
| B | 6 | A |
| C | 4 | A |
| D | 2 | A |
| E | 5 | B |
| F | 3 | B |
| G | 9 | C,D |
| h | 2 | E,F,G, |
a) Draw a project network from the table above
b)
i. What activity(s) is a burst activity?
ii. What activity(s) is a merge activity?
iii. What is the length of the project?
iv. What is the critical path?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts