Question: Activity Duration Dependency START 0 A 8 START B 5 A C 6 B , H D 8 C E 9 D , F F

Activity Duration Dependency
START 0
A 8 START
B 5 A
C 6 B, H
D 8 C
E 9 D, F
F 3 C, I
G 7 START
H 8 G
I 9 H
J 5 I
K 2 J
L 3 J
FINISH 0