Question: Activity Duration Predecessor A 10 B 5 A C 12 A D 12 C E 30 B F 7 B G 9 F H 10
| Activity | Duration | Predecessor |
| A | 10 |
|
| B | 5 | A |
| C | 12 | A |
| D | 12 | C |
| E | 30 | B |
| F | 7 | B |
| G | 9 | F |
| H | 10 | D & E & G |
The critical path is 55 weeks. The customer will pay us a bonus of $100,000 if we can do it in 50 weeks and a bonus of $250,000 if we can do it in 45 weeks.
We can shorten E by 1 to 10 weeks and it will cost is $7500 per week for each week trimmed. We can shorten A to 7 weeks for $40,000. We can shorten H to three weeks by putting all hands on deck but it will cost us $150,000.
What most profitable (for us) crash (or not) do we propose to the customer. Post the activities crashed and the additional profit in the text area for this assignment.