Question: Problem 1 Consider the following project ACTIVITY DURATION PREDECESSOR A 4 B 5 A C 8 A D 3 B E 7 B F 13

Problem 1

Consider the following project

ACTIVITY DURATION PREDECESSOR

A 4 B 5 A C 8 A D 3 B E 7 B F 13 C G 5 D,E,F H 7 G I 9 G J 4 G K 5 H,I, K

1. Draw the project diagram

(Hint : start with just ID and duration - you'll fill in the

ES, EF, LS, LF and S as you work through the question)

2. identify all paths and path duration

3. highlight the critical path

4. calculate the slack for each path

5. calculate the slack for each activity

6. Draw the diagram in the form shown here

using the data from questions 1 to 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!