Question: Given the information in the following table: Activity Duration Predecessor A 8 - B 7 A C 4 A D 5 C, B E 4

Given the information in the following table:

Activity

Duration

Predecessor

A

8

-

B

7

A

C

4

A

D

5

C, B

E

4

A, B

F

6

B, D

G

3

C

H

4

F, G

I

5

E, H

Calculate the Early Start (ES) of activity D

.................

Calculate the Early Finish (EF) of activity C

..........

How long will it take to complete the project?

........

Calculate the Late Finish (LF) of activity H

.......

Calculate the slack (S) of activity G

...

Calculate the Late Start (LS) of activity E

.....