Question: Given the information in the following table: Activity Duration Predecessor A 8 - B 7 A C 4 A D 5 C, B E 4
Given the information in the following table:
| Activity | Duration | Predecessor |
| A | 8 | - |
| B | 7 | A |
| C | 4 | A |
| D | 5 | C, B |
| E | 4 | A, B |
| F | 6 | B, D |
| G | 3 | C |
| H | 4 | F, G |
| I | 5 | E, H |
| Calculate the Early Start (ES) of activity D | ................. |
| Calculate the Early Finish (EF) of activity C | .......... |
| How long will it take to complete the project? | ........ |
| Calculate the Late Finish (LF) of activity H | ....... |
| Calculate the slack (S) of activity G | ... |
| Calculate the Late Start (LS) of activity E | ..... |