Question: Construct CPM Diagram (Activity on Node) Conduct forward pass Conduct backward pass Project Task Duration in weeks Preliminary Design (A) 5 Final Design (B )7
- Construct CPM Diagram (Activity on Node)
- Conduct forward pass
- Conduct backward pass
- Project Task Duration in weeks
- Preliminary Design (A) 5
- Final Design (B )7
- Prepare assembly and test requirements (C )5
- Procure Parts (D) 10
- Assembly (E) 8
- Procure test equipment (F) 12
- Prepare test procedures (G) 7
- Prepare test fixtures (H) 3
T.est (I) 3
- No other tasks can start until preliminary design is completed.
- When preliminary design (A) is completed, final design (B), preparation of assembly and test requirements (C), and parts procurement (D) can start.
- Assembly (E) cannot start until parts are procured (D), final design (B) is complete, and assembly and test requirements (C) are completed.
- Procurement of test equipment (F) and preparation of test procedures (G) cannot start until requirements for assembly and test (C) are available.
- Preparation of test fixtures (H) cannot start until test procedures (G) are available.
- Testing (I) cannot start until assembly (E) is complete, test equipment (F) has been procured, and test fixtures (H) are available.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock