Question: Activity Expected Time Standard Deviation of Time Estimate Immmediate Predecsssor Column 1 A 7 2 - 4 B 3 1 A 1 C 9 3
Activity Expected Time Standard Deviation of Time Estimate Immmediate Predecsssor Column
A
B A
C A
D B C
E B C
F E
G DF
H G
critical path pts
project completion time PTS
probability that the project will take more than time periods pts