Question: Activity Expected Time Standard Deviation of Time Estimate Immmediate Predecsssor Column 1 A 7 2 - 4 B 3 1 A 1 C 9 3

Activity Expected Time Standard Deviation of Time Estimate Immmediate Predecsssor Column1
A 72-4
B 31 A 1
C 93 A 9
D 41 B, C 1
E 51 B, C 1
F 82 E 4
G 81 D,F 1
H 62 G 4
critical path 3 pts
project completion time 3 PTS
probability that the project will take more than 49 time periods 3 pts

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!