Question: Activity Expected Time (weeks) Immediate Predecessor(s) A 3 - B 2 - C 1 A D 3 B E 3 C, D F 5 D
Activity Expected Time (weeks) Immediate Predecessor(s) A 3 - B 2 - C 1 A D 3 B E 3 C, D F 5 D
Calculate the slack for each activity. (Enter your responses as integers.)
| Slack (weeks) | |
| Activity | |
| A | nothing |
| B | nothing |
| C | nothing |
| D | nothing |
| E | nothing |
| F | nothing |