Question: Activity Expected Time (weeks) Immediate Predecessor(s) A 3 - B 2 - C 1 A D 3 B E 3 C, D F 5 D

Activity Expected Time (weeks) Immediate Predecessor(s) A 3 - B 2 - C 1 A D 3 B E 3 C, D F 5 D

Calculate the slack for each activity. (Enter your responses as integers.)

Slack

(weeks)

Activity

A

nothing

B

nothing

C

nothing

D

nothing

E

nothing

F

nothing