Question: The following information is available about a project Activity Activity Time (Weeks) Immediate Predecessor (s) A 4 B 4 C 5 D 4 E 6
The following information is available about a project
| Activity | Activity Time (Weeks) | Immediate Predecessor (s) |
| A | 4 | |
| B | 4 | |
| C | 5 | |
| D | 4 | |
| E | 6 | A |
| F | 2 | B, C, D |
| G | 4 | E, F |
| H | 6 | F |
Compute slack for each activity and determine completion time for the project.
| Activity | Slack |
| A | |
| B | |
| C | |
| D | |
| E | |
| F | |
| G | |
| H |