Question: The following information is available about a project Activity Activity Time (Weeks) Immediate Predecessor (s) A 4 B 4 C 5 D 4 E 6

The following information is available about a project

Activity

Activity

Time

(Weeks)

Immediate

Predecessor (s)

A 4
B 4
C 5
D 4
E 6 A
F 2 B, C, D
G 4 E, F
H 6 F

Compute slack for each activity and determine completion time for the project.

Activity Slack
A
B
C
D
E
F
G
H