Question: Activity G has two immediate predecessors. The earliest finish times for each of these two immediate predecessors are EFA = 12 and EFB = 15.
Activity G has two immediate predecessors. The earliest finish times for each of these two immediate predecessors are EFA and EFB The earliest start time for Activity G is