Question: If an activity has two immediate predecessors with early finish times of 7 and 9, what is the early start time of the activity? 07

If an activity has two immediate predecessors

If an activity has two immediate predecessors

If an activity has two immediate predecessors

If an activity has two immediate predecessors with early finish times of 7 and 9, what is the early start time of the activity? 07 If an activity has two immediate followers with late start times of 11 and 15, what is the late finish time of the activity? O 11 15 If an activity has no followers, its late finish time is the length of the critical path. True False