Question: Activity G has two immediate predecessors. The earliest finish times for each of these two immediate predecessors are EF A =12 and EF B =15.

Activity G has two immediate predecessors. The earliest finish times for each of these two immediate predecessors are EFA=12 and EFB=15. The earliest start time for Activity G is

Group of answer choices

27

15

12

3