Question: Activity Immed. Pred. Time (weeks) A None 2 B A 1 C B 1 D C 2 E C 5 F D, E 5 G
Activity Immed. Pred. Time (weeks) A None 2 B A 1 C B 1 D C 2 E C 5 F D, E 5 G F 1 Construct the CPM network. (10 pts) Determine the earliest and latest activity start and finish times (show in the network). (5 pts) Indicate the critical path and determine the duration of the critical path. (5 pts) Determine the slack for each activity. (5 Pts)