Question: Using the CPM approach to Project Management, what is the critical path and completion time for the for following network diagram? ACTIVITY Precedent Activity Completion
-
Using the CPM approach to Project Management, what is the critical path and completion time for the for following network diagram?
ACTIVITY Precedent Activity Completion Time (days) A NONE 1 B A 1 C B 2 D C 3 E D 4 F E 5 G E 4 H F, G 1 A-B-C-D-E-F-H = 17 days
A-B-C-D-E-G-H = 16 days
A-B-C-D-E-F-G-H = 22 days
A-B-C-D-E-F-H = 19 days
A-B-C-D-E-G-H = 19 days