Question: Activity Immediate Normal Normal Crash Predecessor Time (Days) Cost($) Time (Days) 5,000 8 4,000 8 4 B 12 6,000 10 3,000 6 Crash Cost (5)

Activity Immediate Normal Normal Crash
Activity Immediate Normal Normal Crash Predecessor Time (Days) Cost($) Time (Days) 5,000 8 4,000 8 4 B 12 6,000 10 3,000 6 Crash Cost (5) 6,000 ,000 10,000 3,000 (a) Draw the Precedence Diagram for the above project on a separate sheet of paper and then fill the following table: EF LS LF Slack Critical Path? Immediate Normal ES Acuvity Predecessor Time ASI - DEBT (b) What is the Critical Path? (@) What is the Project Completion Time under normal schedule? days, which activity will you choose and what is the (d) If the total project time has to be crashed by TW extra cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!