Question: Activity: Immediate Pessimistics Probable Optimistic Predecessor(s): Je 10 152 82 Ke 92 8e 7 Le Je 102 be 52 Me 3e 3e 3e Ne 92

Activity: Immediate Pessimistics Probable

Activity: Immediate Pessimistics Probable Optimistic Predecessor(s): Je 10 152 82 Ke 92 8e 7 Le Je 102 be 52 Me 3e 3e 3e Ne 92 5e 12 Je K.Me K.Me L.Ne o 102 7 42 pe 102 8e 3e a. Calculate the expected duration of each activity and find the critical path. + b. Draw the Gantt chart using the expected duration. H c. Calculate variance of the critical path. + d. Calculate the probability that the project will be completed in fewer than 30 time units