Question: Activity Immediate Pred Optimistic Pessimistic Most Likely 3 5 None A 2 6 4 6 None None c 2 6 10 A 5 8 11

Activity Immediate Pred Optimistic Pessimistic
Activity Immediate Pred Optimistic Pessimistic Most Likely 3 5 None A 2 6 4 6 None None c 2 6 10 A 5 8 11 D E A 10 10 16 F B 2 4 6 G B 6 7 14 H 3 3 1 3 2 7 2 4 C E.F GH D.1,J 8 15 J K 4 5 12 1. Construct the PERT CPM network for this project using Activity On Arcs Method. 2. Calculate the ES, LS, EF, LF and Slack for each activity of the project? 3. What is the probability of completing the project within 30 days? Show the steps