Question: Question 1 The information for a project is given in the Table below (time in weeks): Activity Immediate predecessors Optimistic time Most Likely time Pessimistic
Question 1
The information for a project is given in the Table below (time in weeks):
| Activity | Immediate predecessors | Optimistic time | Most Likely time | Pessimistic time |
| A | - | 2 | 3 | 4 |
| B | A | 8 | 8 | 8 |
| C | A | 7 | 9 | 11 |
| D | A | 6 | 6 | 6 |
| E | B, C | 9 | 10 | 11 |
| F | C | 10 | 13 | 16 |
| G | D | 6 | 10 | 14 |
| H | F, E | 10 | 13 | 16 |
| I | G, F | 6 | 7 | 14 |
| J | H, I | 6 | 7 | 8 |
- Draw a network for this project
- Determine the critical path
- Determine the earliest and latest activity times
- Determine slack time for each activity