Question 1

The information for a project is given in the Table below (time in weeks):

Activity

Immediate predecessors

Optimistic time

Most Likely time

Pessimistic time

A

-

2

3

4

B

A

8

8

8

C

A

7

9

11

D

A

6

6

6

E

B, C

9

10

11

F

C

10

13

16

G

D

6

10

14

H

F, E

10

13

16

I

G, F

6

7

14

J

H, I

6

7

8

  1. Draw a network for this project
  2. Determine the critical path
  3. Determine the earliest and latest activity times
  4. Determine slack time for each activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!