Question: Activity Immediate Pred Optimistic Most Likely Pessimistic A None None C 10 None D 11 A 10 10 16 E B 14 B H EF
Activity
Immediate
Pred
Optimistic
Most
Likely
Pessimistic
A
None
None
C
10
None
D
11
A
10
10
16
E
B
14
B
H
EF
G.H
15
D,I,J
12
1. Construct the PERT/CPM network for this project using Activity On Arcs Method.
2. Calculate the ES, LS, EF, LF and Slack for each activity of the project?
3. What is the probability of completing the project within 30 days?
please draw the network on paper.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
