Question: Activity Immediate Predecessor A B C D E F G Time (days) Normal Crash 4 3 6 2 5 2 2 7 5 4 2

Activity Immediate Predecessor A B C D E F G Time

Activity Immediate Predecessor A B C D E F G Time (days) Normal Crash 4 3 6 2 5 2 2 7 5 4 2 Costs ($) Normal Crash 60 90 150 250 40 60 150 250 100 100 115 175 100 240 A A D,B,E mm Nin N 1. Draw the network diagram for the project. 2. Calculate crash cost per activity. 3. What is the normal project duration and the cost associated? 4. Crash the project by 5 days. 5. What is the minimum project duration? Crash the project and identify the cost of completing the project in minimum duration

Step by Step Solution

There are 3 Steps involved in it