Question: ACTIVITY IMMEDIATE PREDECESSOR A TIME (WEEKS) 8 2 6 4 MUA E A A Bfmedia:cm.png% D D E%media:cm.png% F 3 F 4 G 6 a.

ACTIVITY IMMEDIATE PREDECESSOR A TIME (WEEKS) 8 2

ACTIVITY IMMEDIATE PREDECESSOR A TIME (WEEKS) 8 2 6 4 MUA E A A Bfmedia:cm.png% D D E%media:cm.png% F 3 F 4 G 6 a. What is the critical path? A-B-E-G A-B-D-F-G A-C-D-F-G A-C-D-E-G b. How many weeks will it take to complete the project? Number of weeks This is a numeric cell, so please enter numbers only. c. How much slack does activity B have? Slack of activity B weeks