Question: Hello, could you help me solve this question, please? Thank you very much! Question: (a) A project has EIGHT (8) activities listed in the following
Hello, could you help me solve this question, please?
Thank you very much!
Question:
(a) A project has EIGHT (8) activities listed in the following table:
| Activity | Immediate Predecessor (s) | Time (Weeks) | Activity | Immediate Predecessor (s) | Time (Weeks) |
| A | - | 2 | E | C | 3 |
| B | A | 5 | F | C | 7 |
| C | A | 3 | G | D, E | 2 |
| D | B | 4 | H | F | 3 |
(i) Use the GRAPH PAPER provided to construct a Gantt chart for the above project. [Note: You are to attach the graph paper to the page where this question is answered].
(ii) What is the expected project duration in weeks?
(b) Explain the following TWO (2) terms in lean operations:
(i) Kanban.
(ii) Toyota production system (TPS)