(a) A project has EIGHT (8) activities listed in the following table:

Activity

Immediate Predecessor (s)

Time (Weeks)

Activity

Immediate Predecessor (s)

Time (Weeks)

A

-

2

E

C

3

B

A

5

F

C

7

C

A

3

G

D, E

2

D

B

4

H

F

3

(i) Use the GRAPH PAPER provided to construct a Gantt chart for the above project. [Note: You are to attach the graph paper to the page where this question is answered].

(ii) What is the expected project duration in weeks?

(b) Explain the following TWO (2) terms in lean operations:

(i) Kanban.

(ii) Toyota production system (TPS)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!